Question

A buyer's OTP makes vacant possession on completion a condition. On the completion date, the seller's tenant is still in occupation. What may the buyer do?

  1. Option A: Treat the contract as ended and claim damages, because a condition has been breached
  2. Option B: Complete and then sue the tenant in the Small Claims Tribunals
  3. Option C: Nothing, because vacant possession is a warranty
  4. Option D: Claim damages only, because breach of any term gives damages only
Show answerHide answer

A Answer: A. Treat the contract as ended and claim damages, because a condition has been breached

Why

Breach of a condition (a major term) lets the innocent party terminate and claim damages; breach of a warranty gives damages only (source: Singapore Statutes Online). The parties expressly made vacant possession a condition.

Sources

  • Singapore Statutes Online — Damages are the default remedy for breach of contract, putting the innocent party where it would have been had the contract been performed. Breach of a…

Checked against the official sources linked above. A practice question written by RES Prep in the style of the RES exam, not a past exam question. Rules change, so check the linked sources before relying on them.

Practise 2.1 Law of contract

Work through every question on this topic with instant marking, or sit a timed mock of Paper 1.

More questions on Law of contract

All RES practice questions with answers