Paper 2 · CU3 · Section A practice question

Works to a conserved building: permission

Question

Which statement about works to a conserved building is correct?

  1. Option A: Only works visible from the street need Conservation Permission
  2. Option B: BCA building plan approval replaces the need for URA Conservation Permission
  3. Option C: Repair and maintenance works need no approval from URA
  4. Option D: Any works to a conserved building need URA Conservation Permission before they start
Show answerHide answer

D Answer: D. Any works to a conserved building need URA Conservation Permission before they start

Why

Any works to a conserved building need Conservation Permission before they start, whether or not BCA approval is also needed; BCA building plan clearance follows Conservation Permission for works that need it (source: URA). Minor repair works fall under the simpler Category 3 process but still need Conservation Permission, which is the trap.

Sources

  • URA — Any works to a conserved building need URA Conservation Permission before the works start, whether or not BCA approval is also needed. Category 1 and 2 works…

Checked against the official sources linked above. A practice question written by RES Prep in the style of the RES exam, not a past exam question. Rules change, so check the linked sources before relying on them.

Practise 3.13 Marketing of conservation properties

Work through every question on this topic with instant marking, or sit a timed mock of Paper 2.

More questions on Marketing of conservation properties

All RES practice questions with answers