Paper 1 · CU2 · Section A practice question

EC MOP and privatisation for 2026 sites

Question

For new executive condominium (EC) sites whose land tenders close on or after 8 May 2026, what are the minimum occupation period (MOP) and the time until full privatisation?

  1. Option A: MOP 5 years; fully privatised after 10 years
  2. Option B: MOP 10 years; fully privatised after 15 years
  3. Option C: MOP 10 years; fully privatised after 10 years
  4. Option D: MOP 5 years; fully privatised after 15 years
Show answerHide answer

B Answer: B. MOP 10 years; fully privatised after 15 years

Why

For EC sites with land tenders closing on or after 8 May 2026, the MOP is 10 years, full privatisation comes after 15 years, and the Deferred Payment Scheme is not available (source: MND). The old rule, still applying to earlier sites, was a 5-year MOP with full privatisation after 10 years (source: stackedhomes.com).

Sources

  • MND — For EC sites with land tenders closing on or after 8 May 2026, the MOP is 10 years, full privatisation is after 15 years, and the Deferred Payment Scheme is…
  • stackedhomes.com — For ECs on earlier sites, the MOP is 5 years; after MOP they can be sold to SCs and SPRs, and after 10 years they are fully privatised and can be sold to…

Checked against the official sources linked above. A practice question written by RES Prep in the style of the RES exam, not a past exam question. Rules change, so check the linked sources before relying on them.

Practise 2.12 Planning and development of land

Work through every question on this topic with instant marking, or sit a timed mock of Paper 1.

More questions on Planning and development of land

All RES practice questions with answers