Question
How often must URA review the Master Plan under the Planning Act?
- Option A: At least once every 10 years
- Option B: Every year
- Option C: Only when a developer applies for rezoning
- Option D: At least once every 5 years
Show answerHide answer
D Answer: D. At least once every 5 years
Why
URA, as the competent authority, must review the Master Plan at least once every 5 years (Planning Act s8) (source: Singapore Statutes Online).
Sources
- Singapore Statutes Online — URA (the competent authority) must review the Master Plan at least once every 5 years (Planning Act s8).