Paper 2 · CU4 · Section A practice question

Can a developer change the prescribed S&P?

Question

A developer wants to change a clause in the prescribed S&P for strata units in its licensed project. Which is correct?

  1. Option A: The S&P must be in Form 4, and the developer may change it freely if the buyer agrees
  2. Option B: There is no prescribed form, so the developer may use its own contract
  3. Option C: The S&P must be in Form 5, and any change needs the Controller's approval unless it is one of URA's pre-approved amendments
  4. Option D: Changes are allowed without approval once the S&P has been delivered to the buyer
Show answerHide answer

C Answer: C. The S&P must be in Form 5, and any change needs the Controller's approval unless it is one of URA's pre-approved amendments

Why

The S&P for a licensed project must be in the prescribed form: Form 4 for landed/non-strata and Form 5 for strata units; changes need the Controller's approval except URA's pre-approved amendments (source: Singapore Statutes Online).

Sources

  • Singapore Statutes Online — The S&P for a unit in a licensed project must be in the prescribed form: Form 4 (landed/non-strata) or Form 5 (strata units). Changes need the Controller's…

Checked against the official sources linked above. A practice question written by RES Prep in the style of the RES exam, not a past exam question. Rules change, so check the linked sources before relying on them.

Practise 4.1 Sale of uncompleted private properties

Work through every question on this topic with instant marking, or sit a timed mock of Paper 2.

More questions on Sale of uncompleted private properties

All RES practice questions with answers