Question
A developer wants to change a clause in the prescribed S&P for strata units in its licensed project. Which is correct?
- Option A: The S&P must be in Form 4, and the developer may change it freely if the buyer agrees
- Option B: There is no prescribed form, so the developer may use its own contract
- Option C: The S&P must be in Form 5, and any change needs the Controller's approval unless it is one of URA's pre-approved amendments
- Option D: Changes are allowed without approval once the S&P has been delivered to the buyer
Show answerHide answer
C Answer: C. The S&P must be in Form 5, and any change needs the Controller's approval unless it is one of URA's pre-approved amendments
Why
The S&P for a licensed project must be in the prescribed form: Form 4 for landed/non-strata and Form 5 for strata units; changes need the Controller's approval except URA's pre-approved amendments (source: Singapore Statutes Online).
Sources
- Singapore Statutes Online — The S&P for a unit in a licensed project must be in the prescribed form: Form 4 (landed/non-strata) or Form 5 (strata units). Changes need the Controller's…