Paper 2 · CU4 · Section A practice question

Deadline for legal completion of a new launch

Question

Under the prescribed S&P for a licensed housing project, by when must legal completion take place?

  1. Option A: By the stipulated date or, at the latest, 3 years after vacant possession is delivered
  2. Option B: Within 14 days after vacant possession is delivered
  3. Option C: On the date the CSC is issued
  4. Option D: Within 12 months after TOP
Show answerHide answer

A Answer: A. By the stipulated date or, at the latest, 3 years after vacant possession is delivered

Why

Legal completion is due by the stipulated date or, at the latest, 3 years after vacant possession is delivered (source: Singapore Statutes Online). It is not tied to the CSC date, which is why the 13% stakeholder arrangement exists (source: Supreme Court judgment).

Sources

  • Singapore Statutes Online — Under the prescribed S&P, legal completion is due by the stipulated date or, at latest, 3 years after vacant possession is delivered.
  • Supreme Court judgment — The final 15% of the price is dealt with in one of two ways. If legal completion happens before the CSC is issued: 2% to the developer on completion and 13%…

Checked against the official sources linked above. A practice question written by RES Prep in the style of the RES exam, not a past exam question. Rules change, so check the linked sources before relying on them.

Practise 4.1 Sale of uncompleted private properties

Work through every question on this topic with instant marking, or sit a timed mock of Paper 2.

More questions on Sale of uncompleted private properties

All RES practice questions with answers