Question
Under the prescribed S&P for a licensed housing project, when must the buyer pay each progress instalment?
- Option A: On the date stated in the original payment schedule, whether or not the stage is complete
- Option B: Within 3 weeks of the stage being completed on site
- Option C: Within 14 days of receiving the developer's notice and the architect's certificate for that stage
- Option D: Within 8 weeks of the architect's certificate
Show answerHide answer
C Answer: C. Within 14 days of receiving the developer's notice and the architect's certificate for that stage
Why
Each instalment is payable within 14 days of the buyer receiving the developer's notice and the architect's certificate; late payment attracts interest (source: Singapore Statutes Online). Payments fall due by stage completion as certified, not on fixed calendar dates.
Sources
- Singapore Statutes Online — Under the prescribed S&P, the buyer must pay each progress instalment within 14 days of receiving the developer's notice and architect's certificate; late…